Abstract
The Finnish pressure equipment legislation was recently
renewed. According to the new legislation, a boiler plant
hazard assessment must be carried out in certain boiler
plants. The plant's owner and holder must identify
potential hazards, their causes and consequences.
Furthermore, the significance of the identified hazard
scenarios and the appropriateness of the risk reduction
measures and safety precautions must be assessed. All
this, i.e. the description of the plant's hazard
assessment process and its results, must be in the form
of a written report to be presented to the inspection
body for approval. The paper presents an approach to
fulfil the requirement, and the experiences based on
several projects carried out by VTT.
Original language | English |
---|---|
Title of host publication | Proceedings of the European Safety and Reliability Conference, ESREL 2005 |
Place of Publication | Leiden |
Publisher | CRC Press |
Pages | 1707 - 1713 |
ISBN (Electronic) | 0-415-38341-2 |
ISBN (Print) | 0-415-38340-4 |
Publication status | Published - 2005 |
MoE publication type | A4 Article in a conference publication |
Event | European Safety and Reliability Conference, ESREL 2005 - Tricity, Poland Duration: 27 Jun 2005 → 30 Jun 2005 |
Conference
Conference | European Safety and Reliability Conference, ESREL 2005 |
---|---|
Abbreviated title | ESREL 2005 |
Country/Territory | Poland |
City | Tricity |
Period | 27/06/05 → 30/06/05 |