TY - JOUR
T1 - Main Findings, Remaining Uncertainties and Lessons Learned from the OECD/NEA BSAF Project
AU - Pellegrini, M.
AU - Herranz, L.
AU - Sonnenkalb, M.
AU - Lind, T.
AU - Maruyama, Y.
AU - Gauntt, R.
AU - Bixler, N.
AU - Morreale, A.
AU - Dolganov, K.
AU - Sevon, Tuomo
AU - Jacquemain, D.
AU - Journeau, C.
AU - Song, J. H.
AU - Nishi, Y.
AU - Mizokami, S.
PY - 2020/9/1
Y1 - 2020/9/1
N2 - The Organisation for Economic Co-operation and Development (OECD)/Nuclear Energy Agency (NEA) Benchmark Study of the Accident at the Fukushima Daiichi Nuclear Power Station (BSAF), which started in 2012 and continued until 2018, was one of the earliest responses to the accident at Fukushima Daiichi. The project, divided into two phases, addressed the investigation of the accident at Units 1, 2, and 3 by severe accident (SA) codes until 500 h, focusing on thermal hydraulics, core relocation, molten corium concrete interaction (MCCI), and fission product release and transport. The objectives of the BSAF were to make up plausible scenarios based primarily on SA forensic analysis, support the decommissioning, and inform SA code modeling. The analysis and comparison among the institutes have brought up vital insights regarding the accident progression, identifying periods of core meltdown and relocation and reactor pressure vessel (RPV) and primary containment vessel (PCV) leakage/failure through the comparison of pressure, water level, and containment atmosphere monitoring system (CAMS) signatures. The combination of code results and inspections (muon radiography, PCV inspection) has provided a picture of the current status of the debris distribution and plant status. All units present a large relocation of core materials and all of them present ex-vessel debris with Unit 1 and Unit 3 showing evidence of undergoing MCCI. Uncertainties have been identified, in particular on the time and magnitude of events such as corium relocation in the RPV and into the cavity floor and RPV and PCV rupture events. Main uncertainties resulting from the project are the large and continuous MCCI progression predicted by basically all the SA codes and the leak pathways from the RPV to the PCV and the PCV to the reactor building and environment. The BSAF project represents a pioneering exercise that has set the basis and provided lessons learned not only for code improvement but also for the development of new related projects to investigate in detail further aspects of the Fukushima Daiichi accident.
AB - The Organisation for Economic Co-operation and Development (OECD)/Nuclear Energy Agency (NEA) Benchmark Study of the Accident at the Fukushima Daiichi Nuclear Power Station (BSAF), which started in 2012 and continued until 2018, was one of the earliest responses to the accident at Fukushima Daiichi. The project, divided into two phases, addressed the investigation of the accident at Units 1, 2, and 3 by severe accident (SA) codes until 500 h, focusing on thermal hydraulics, core relocation, molten corium concrete interaction (MCCI), and fission product release and transport. The objectives of the BSAF were to make up plausible scenarios based primarily on SA forensic analysis, support the decommissioning, and inform SA code modeling. The analysis and comparison among the institutes have brought up vital insights regarding the accident progression, identifying periods of core meltdown and relocation and reactor pressure vessel (RPV) and primary containment vessel (PCV) leakage/failure through the comparison of pressure, water level, and containment atmosphere monitoring system (CAMS) signatures. The combination of code results and inspections (muon radiography, PCV inspection) has provided a picture of the current status of the debris distribution and plant status. All units present a large relocation of core materials and all of them present ex-vessel debris with Unit 1 and Unit 3 showing evidence of undergoing MCCI. Uncertainties have been identified, in particular on the time and magnitude of events such as corium relocation in the RPV and into the cavity floor and RPV and PCV rupture events. Main uncertainties resulting from the project are the large and continuous MCCI progression predicted by basically all the SA codes and the leak pathways from the RPV to the PCV and the PCV to the reactor building and environment. The BSAF project represents a pioneering exercise that has set the basis and provided lessons learned not only for code improvement but also for the development of new related projects to investigate in detail further aspects of the Fukushima Daiichi accident.
KW - BSAF project
KW - Fukushima accident
KW - OECD/NEA
KW - severe accident code
UR - http://www.scopus.com/inward/record.url?scp=85083585614&partnerID=8YFLogxK
U2 - 10.1080/00295450.2020.1724731
DO - 10.1080/00295450.2020.1724731
M3 - Article
AN - SCOPUS:85083585614
SN - 0029-5450
VL - 206
SP - 1449
EP - 1463
JO - Nuclear Technology
JF - Nuclear Technology
IS - 9
ER -