Abstract
In this paper we examine the current project risk
management activities in three Finnish project
organizations. Our aim is to describe the anatomy of the
formative risk management process and related embedded
activities currently used to identify, analyse or
mitigate risks in global engineering projects. This study
shows that there is a difference between written risk
management procedures, managers' ambitions towards risk
management and how risk management is actually realized
in projects. We also analysed how systematic and
participative the risk management activities are during
the project life cycle. We identified two discontinuity
points: the first one is in the project start-up and
handover from the sales to the project team, in a phase
where the main decisions affecting the risks in the
project have
already been made and where the risk knowledge should be
transferred from the sales team to the project team. The
other discontinuity point is at the end of the project
where the risk information from each project should be
gathered within a project team and utilized in other
projects. Even though there were discontinuities in the
formal risk management processes within the projects, the
risks were successfully managed in the case companies.
This could imply that other processes and mechanisms are
used parallel to the formal risk management process.
These non-formal actions are used to cover the
discontinuity points and the areas where the formal risk
management lacks the flexibility and agility required.
Original language | English |
---|---|
Title of host publication | Proceedings of the 13th International Conference on Productivity and Quality Research, ICPQR 2008 |
Editors | J. Kujala, P. Iskanius |
Place of Publication | Oulu |
Publisher | University of Oulu |
Pages | 826-836 |
ISBN (Print) | 978-951-42-8827-2 |
Publication status | Published - 2008 |
MoE publication type | A4 Article in a conference publication |
Event | 13th International Conference on Productivity and Quality Research, ICPQR 2008 - Oulu, Finland Duration: 25 Jun 2008 → 27 Jun 2008 |
Conference
Conference | 13th International Conference on Productivity and Quality Research, ICPQR 2008 |
---|---|
Abbreviated title | ICPQR 2008 |
Country/Territory | Finland |
City | Oulu |
Period | 25/06/08 → 27/06/08 |
Keywords
- risk management
- project management