Practical determination of probability of failure in risk-based inspection and life management of coal power plants

A. Jovanovic, Pertti Auerkari, J.M. Bareiss

    Research output: Chapter in Book/Report/Conference proceedingChapter or book articleProfessional

    Abstract

    This chapter discusses the method for determination of probability of failure in risk-based inspection (RBI) and life management of coal power plants. It begins by reviewing the basic principles and requirements for RBI in CWA 15740:2008 before examining the RIMAP procedure (Risk-based Inspection and Maintenance Procedures for European Industry). The chapter also covers the requirements for a PoF (Probability of Failure) analysis, and assesses PoF and damage/failure rates data. The chapter concludes with sections on the RIMAP method for determination of PoF, and practical applications of the approach.
    Original languageEnglish
    Title of host publicationCoal Power Plant Materials and Life Assessment
    Subtitle of host publicationDevelopments and Applications
    EditorsAhmed Shibli
    Place of PublicationCambridge
    PublisherElsevier
    Chapter11
    Pages288-317
    ISBN (Print)978-0-85709-431-5
    DOIs
    Publication statusPublished - 2014
    MoE publication typeD2 Article in professional manuals or guides or professional information systems or text book material

    Publication series

    SeriesWoodhead publishing series in energy
    Volume62
    ISSN2044-9364

    Keywords

    • risk-based inspection
    • maintenance
    • plant life assessment
    • plant life management
    • power plants

    Fingerprint

    Dive into the research topics of 'Practical determination of probability of failure in risk-based inspection and life management of coal power plants'. Together they form a unique fingerprint.