TY - BOOK
T1 - Requirements Management and Critical Decision Points
AU - Koppinen, Tiina
AU - Kiviniemi, Arto
N1 - Project code: 1026
PY - 2007
Y1 - 2007
N2 - In this working paper, a study carried out as part of the
second phase of the Virtual Building Environments
research and development project is reported. The working
paper covers work done to determine the interface between
requirements management and critical decision points. The
report first defines the processes and critical decision
points within building architecture, engineering,
construction and operation (AECO) project lifecycle for
which users require information exchange. Then, detailed
information needs in each critical decision point are
specified. Finally, the actors sending and receiving
information within the project lifecycle are identified
and the associated, required information content of BIMs
is determined.
Within this working paper, the life cycle of the building
is divided into five phases: pre-project, design &
pre-construction, construction, post-construction and
operation & maintenance. The actors in the process are
the owner, end-users, marketing & sales, project
management, designers, constructors, facilities
management and authorities. Only "hard gates", critical
decisions that involve a permission from the financial
authority (the owner) to proceed, are studied in detail.
"Soft gates", decisions and selections made by the
individual designers or the design team during the
process, are not documented. The critical decision points
in the process are 1) project decision and investment
decision during pre-project phase, 2) decision to
construct after design & pre-construction phase, 3)
commissioning after construction phase, 4) release of
guarantees after post-construction phase, and 5) the
decision to demolish the building in the end of the
building's life cycle.
Many of the information needs during the process relate
back to the project requirements. Requirements set the
basis for the design and, throughout the process, the
results of the project must be compared with the
requirements in order to define the level of requirement
fulfilment. This emphasises the importance of capturing
and documenting initial requirements and updating the
evolving requirements during the process. Current
technologies also enable use of more complicated and
automated analyses as a basis of more informed
decision-making.
AB - In this working paper, a study carried out as part of the
second phase of the Virtual Building Environments
research and development project is reported. The working
paper covers work done to determine the interface between
requirements management and critical decision points. The
report first defines the processes and critical decision
points within building architecture, engineering,
construction and operation (AECO) project lifecycle for
which users require information exchange. Then, detailed
information needs in each critical decision point are
specified. Finally, the actors sending and receiving
information within the project lifecycle are identified
and the associated, required information content of BIMs
is determined.
Within this working paper, the life cycle of the building
is divided into five phases: pre-project, design &
pre-construction, construction, post-construction and
operation & maintenance. The actors in the process are
the owner, end-users, marketing & sales, project
management, designers, constructors, facilities
management and authorities. Only "hard gates", critical
decisions that involve a permission from the financial
authority (the owner) to proceed, are studied in detail.
"Soft gates", decisions and selections made by the
individual designers or the design team during the
process, are not documented. The critical decision points
in the process are 1) project decision and investment
decision during pre-project phase, 2) decision to
construct after design & pre-construction phase, 3)
commissioning after construction phase, 4) release of
guarantees after post-construction phase, and 5) the
decision to demolish the building in the end of the
building's life cycle.
Many of the information needs during the process relate
back to the project requirements. Requirements set the
basis for the design and, throughout the process, the
results of the project must be compared with the
requirements in order to define the level of requirement
fulfilment. This emphasises the importance of capturing
and documenting initial requirements and updating the
evolving requirements during the process. Current
technologies also enable use of more complicated and
automated analyses as a basis of more informed
decision-making.
KW - building information model
KW - decision point
KW - decision making
KW - design process
M3 - Report
T3 - VTT Working Papers
BT - Requirements Management and Critical Decision Points
PB - VTT Technical Research Centre of Finland
CY - Espoo
ER -