Abstract
In this paper we suggest that there are two types of
project strategy: project's business strategy and
project's execution strategy. The project's business
strategy focuses on the purpose of the project,
addressing the question: Why does the project exist? The
project's execution strategy addresses the
question: How is the project executed? We conduct a
conceptual analysis of the distinctive contents of
these two project strategy types by focusing on the
project management literature. We also analyse the
links of the two types of project strategy to other
stakeholders in the project's environment than the
parent organisation, and to other contextual factors in
the project's environment. Our analysis suggests
that the formation of these two types of project strategy
is a complex process that is affected not only by
the corporate level strategies and guidelines of the
project's parent firm, but also by stakeholders and
contextual factors in the project's context. In the
empirical study, we investigate risk strategies and risk
management strategies in eight power plant delivery
projects in one major energy system supplier
company. For the empirical study, we define the
corresponding project strategy concepts in the project
risk management application area. Risk strategy
corresponds to the project's business strategy by
addressing the "why" question for the management of risks
being in place. The risk strategy includes the
project's approach to different kinds of risks, and it
includes statements of the project's attitude to risks:
for example, what kinds of risks are acceptable and what
kind of risks must be avoided. Risk
management strategy corresponds to the project's
execution strategy by including the project's approach
to organize its risk management in a most effective way
("how") to meet goals for risk management as
defined in risk strategy. The results of our study
suggests that in addition to the parent firm, also the
customer, subcontractors and local authorities are major
stakeholders that have an influence of strategy
formation of the two types of the project's strategy. The
influence of these stakeholders on the project's
strategies varied, depending on the case project. The
parent firm has a significant influence on the risk
strategies (or business strategies) of the case projects.
The other stakeholders' impact can be seen more
clearly on the risk management strategies (or execution
strategies). The parent firm thus sets the purpose
of a project, but the project sets its management
strategies by taking into account the contextual factors
and stakeholders.
| Original language | English |
|---|---|
| Title of host publication | IRNOP-Conference 2009 |
| Subtitle of host publication | Abstracts |
| Place of Publication | Berlin |
| Number of pages | 20 |
| Publication status | Published - 2009 |
| MoE publication type | A4 Article in a conference publication |
| Event | 9th International Conference of the International Research Network on Organising by Projects: IRNOP IX Research Conference - Berlin, Germany Duration: 11 Oct 2009 → 13 Oct 2009 |
Conference
| Conference | 9th International Conference of the International Research Network on Organising by Projects |
|---|---|
| Country/Territory | Germany |
| City | Berlin |
| Period | 11/10/09 → 13/10/09 |
Keywords
- project strategy
- project s business strategy
- project s execution strategy
- strategy formation
- contingencies
- context
- stakeholders
Fingerprint
Dive into the research topics of 'Two types of project strategy - empirical illustrations in project risk management'. Together they form a unique fingerprint.Cite this
- APA
- Author
- BIBTEX
- Harvard
- Standard
- RIS
- Vancouver